ITAC Assessment: AM0281
ITAC logo
ITAC Assessment: AM0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Shrimp & Catfish
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 32,600
ft2
Annual Production 4,300,000
lb
Production Hrs. Annual 2,280
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $89,064 1,570,047
kWh
Electricity Demand $21,769 7,063
kW-mo/yr
Electricity Fees $3,519 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $114,418 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $99,948

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings By-product Production Savings
01 3.1191: Change procedures / equipment / operating conditions $95,600 $1,500 - - - $80,200
-
lb
$15,400
02 2.3212: Optimize plant power factor $14,320 $14,320 - $14,320
-
kW-mo/yr
- - -
03 2.4133: Use most efficient type of electric motors $150 $180 $70
1,465
kWh
$80
-
kW-mo/yr
- - -
04 2.3132: Recharge batteries on during off-peak demand periods $2,250 $2,370 - $2,250
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $950 $470 $550
11,430
kWh
$400
-
kW-mo/yr
- - -
06 2.8123: Pay utility bills on time $903 - - - $903 - -
07 2.8112: Combine utility meters $245 - - - $245 - -
TOTAL RECOMMENDED $114,418 $18,840 $620
12,895
kWh
$17,050
-
kW-mo/yr
$1,148 $80,200
-
lb
$15,400
TOTAL IMPLEMENTED $99,948 $4,340 $550
11,430
kWh
$2,650
-
kW-mo/yr
$1,148 $80,200
-
lb
$15,400
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs