ITAC Assessment: AM0274
ITAC logo
ITAC Assessment: AM0274
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Tank heads and mold boards
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $50
M
to 100
M
# of Employees 220
Plant Area 200,000
ft2
Annual Production 122,500
pieces
Production Hrs. Annual 5,020
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $163,643 6,551,876
kWh
Electricity Demand $147,132 17,479
kW-mo/yr
Natural Gas $546,052 253,787
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,244 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,592

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.3134: Shift from daytime to nighttime operation $18,652 - - $18,652
-
kW-mo/yr
-
02 2.3212: Optimize plant power factor $15,365 $9,000 - $15,365
-
kW-mo/yr
-
03 2.4133: Use most efficient type of electric motors $340 $790 $180
6,155
kWh
$160
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,600 $1,000 $5,600
193,435
kWh
- -
05 2.4314: Use synthetic lubricant $760 - $330
11,430
kWh
$430
-
kW-mo/yr
-
06 2.7111: Reduce illumination to minimum necessary levels $640 $100 $310
10,551
kWh
$330
-
kW-mo/yr
-
07 3.7131: Use a rag recycle service $5,340 $75 - - $5,340
-
lb
08 3.7198: Reduce / eliminate use of disposable product $2,637 $110 - - $2,637
-
lb
09 3.1182: Make a new by-product $910 - - - $910
-
lb
TOTAL RECOMMENDED $50,244 $11,075 $6,420
221,571
kWh
$34,937
-
kW-mo/yr
$8,887
-
lb
TOTAL IMPLEMENTED $31,592 $11,075 $6,420
221,571
kWh
$16,285
-
kW-mo/yr
$8,887
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs