Assessment Year | 1996 |
---|---|
Principal Product | Fiberglass roofing shingle mats |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 56 |
Plant Area |
24,000
ft2
|
Annual Production | 3,100,000
thousand feet
|
Production Hrs. Annual | 8,592
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $422,961 | 12,501,759 |
kWh
|
$0.034 |
Electricity Demand | $198,377 | 26,218 |
kW-mo/yr
|
$7.57 |
Electricity Fees | $180 | - |
|
- |
Natural Gas | $421,239 | 213,811 |
MMBtu
|
$1.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $325,930 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $211,110 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $167,000 | $73,600 | - | - |
$167,000
-
MMBtu
|
- | |
02 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $7,330 | $400 | - | - |
$7,330
-
MMBtu
|
- | |
03 | 2.7124: Make a practice of turning off lights when not needed | $2,830 | - |
$1,620
81,184
kWh
|
$1,210
-
kW-mo/yr
|
- | - | |
04 | 3.1162: Use less wasteful packaging | $97,900 | - | - | - | - |
$97,900
-
lb
|
|
05 | 3.1182: Make a new by-product | $36,780 | - | - | - | - |
$36,780
-
lb
|
|
06 | 3.5313: Increase amount of waste recovered for resale | $14,090 | - | - | - | - |
$14,090
-
lb
|
|
TOTAL RECOMMENDED | $325,930 | $74,000 |
$1,620
81,184
kWh
|
$1,210
-
kW-mo/yr
|
$174,330
-
MMBtu
|
$148,770
-
lb
|
||
TOTAL IMPLEMENTED | $211,110 | $74,000 | - | - |
$174,330
-
MMBtu
|
$36,780
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs