| Assessment Year | 1996 |
|---|---|
| Principal Product | Custom compounding of purchased resins |
| NAICS |
n/a
|
| SIC | 3087: Custom Compounding of Purchased Plastics Resins |
| Sales Range | $10 M to 50M |
| # of Employees | 140 |
| Plant Area |
128,000
ft2
|
| Annual Production | 40,000,000
lb
|
| Production Hrs. Annual | 8,664
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $334,876 | 10,859,027 |
kWh
|
$0.031 |
| Electricity Demand | $140,223 | 20,843 |
kW-mo/yr
|
$6.73 |
| Electricity Fees | $8,479 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,810 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $19,900 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,720 | - | - |
$7,720
-
kW-mo/yr
|
- | - | |
| 02 | 2.7145: Install skylights | $6,480 | $13,860 |
$6,480
294,549
kWh
|
- | - | - | |
| 03 | 2.2511: Insulate bare equipment | $4,260 | $230 |
$4,260
194,607
kWh
|
- | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $1,840 | $1,140 |
$970
44,256
kWh
|
$870
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,650 | $760 |
$60
2,931
kWh
|
$50
-
kW-mo/yr
|
- | $1,540 | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $1,350 | $480 |
$310
14,068
kWh
|
$1,040
-
kW-mo/yr
|
- | - | |
| 07 | 2.4314: Use synthetic lubricant | $1,190 | - |
$660
29,894
kWh
|
$530
-
kW-mo/yr
|
- | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,020 | $20 |
$570
26,084
kWh
|
$450
-
kW-mo/yr
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $980 | $190 |
$250
11,430
kWh
|
$730
-
kW-mo/yr
|
- | - | |
| 10 | 3.4154: Eliminate leaks in water lines and valves | $2,320 | $360 | - | - |
$2,320
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $28,810 | $17,040 |
$13,560
617,819
kWh
|
$11,390
-
kW-mo/yr
|
$2,320
-
Tgal
|
$1,540 | ||
| TOTAL IMPLEMENTED | $19,900 | $17,040 |
$12,900
587,925
kWh
|
$3,140
-
kW-mo/yr
|
$2,320
-
Tgal
|
$1,540 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs