Assessment Year | 1996 |
---|---|
Principal Product | School furniture, including dorm and lab furniture |
NAICS |
n/a
|
SIC | 2531: Public Building and Related Furniture |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
327,000
ft2
|
Annual Production | 13,326
pieces
|
Production Hrs. Annual | 1,992
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,067 | 1,180,832 |
kWh
|
$0.050 |
Electricity Demand | $52,821 | 6,486 |
kW-mo/yr
|
$8.14 |
Natural Gas | $18,063 | 4,343 |
MMBtu
|
$4.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,740 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,165 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,660 | $510 |
$2,660
65,651
kWh
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $735 | $1,230 |
$185
4,689
kWh
|
$60
-
kW-mo/yr
|
- | $490 | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $575 | $40 |
$225
5,569
kWh
|
$350
-
kW-mo/yr
|
- | - | |
04 | 2.6212: Turn off equipment during breaks, reduce operating time | $500 | - |
$500
12,309
kWh
|
- | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $150 | $150 |
$70
1,758
kWh
|
$80
-
kW-mo/yr
|
- | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $44,120 | $960 | - | - |
$44,120
-
lb
|
- | |
TOTAL RECOMMENDED | $48,740 | $2,890 |
$3,640
89,976
kWh
|
$490
-
kW-mo/yr
|
$44,120
-
lb
|
$490 | ||
TOTAL IMPLEMENTED | $48,165 | $2,850 |
$3,415
84,407
kWh
|
$140
-
kW-mo/yr
|
$44,120
-
lb
|
$490 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs