ITAC Assessment: AM0259
ITAC logo
ITAC Assessment: AM0259
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Grinding & electroplating of metals, hard chrome and electro
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $1
M
to 5
M
# of Employees 100
Plant Area
n/a
Annual Production 101,744
thousand feet
Production Hrs. Annual 4,016
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $135,351 3,234,467
kWh
Electricity Demand $56,804 8,539
kW-mo/yr
Electricity Fees $6,360 -
Natural Gas $88,959 17,289
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,440 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,310

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,920 $9,040 $1,400
63,599
kWh
$2,520
-
kW-mo/yr
- -
02 2.2511: Insulate bare equipment $2,800 $110 - - $2,800
-
MMBtu
-
03 2.7141: Lower light fixtures in high ceiling areas $1,480 $770 $530
24,326
kWh
$950
-
kW-mo/yr
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $1,350 $500 - - $1,350
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,150 $200 $1,150
52,169
kWh
- - -
06 2.2511: Insulate bare equipment $1,030 $850 - - $1,030
-
MMBtu
-
07 2.7111: Reduce illumination to minimum necessary levels $510 $175 $190
8,792
kWh
$320
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $260 $110 $60
2,931
kWh
$200
-
kW-mo/yr
- -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $90 $180 $30
1,465
kWh
$60
-
kW-mo/yr
- -
10 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,850 $40,000 - - - $5,850
-
gal
TOTAL RECOMMENDED $18,440 $51,935 $3,360
153,282
kWh
$4,050
-
kW-mo/yr
$5,180
-
MMBtu
$5,850
-
gal
TOTAL IMPLEMENTED $8,310 $11,055 $2,830
128,956
kWh
$3,100
-
kW-mo/yr
$2,380
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs