Assessment Year | 1995 |
---|---|
Principal Product | Welded steel tube, fabricated steel line pipe and mechanical |
NAICS |
n/a
|
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $10 M to 50M |
# of Employees | 116 |
Plant Area |
160,000
ft2
|
Annual Production | 63,000
ton
|
Production Hrs. Annual | 6,048
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $692,210 | 17,924,971 |
kWh
|
$0.039 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,300 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $20,880 | $69,400 |
$27,100
-
kWh
|
$(-6,220.0)
-
MMBtu
|
- | - | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $21,630 | - |
$21,630
-
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,100 | $800 |
$2,100
90,270
kWh
|
- | - | - | - | |
04 | 2.4314: Use synthetic lubricant | $1,680 | - |
$1,680
56,272
kWh
|
- | - | - | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $390 | $690 |
$390
11,137
kWh
|
- | - | - | - | |
06 | 3.7198: Reduce / eliminate use of disposable product | $7,450 | $7,900 | - | - | - | - |
$7,450
-
lb
|
|
07 | 3.7131: Use a rag recycle service | $2,000 | - | - | - | - | - |
$2,000
-
lb
|
|
08 | 3.8211: Convert to aqueous cleaning system | $1,060 | $3,600 | - | - | - |
$1,060
-
gal
|
- | |
09 | 3.6192: Use a less expensive method of waste removal | $560 | - | - | - |
$560
-
gal
|
- | - | |
10 | 3.6192: Use a less expensive method of waste removal | $130 | - | - | - | - | - |
$130
-
lb
|
|
TOTAL RECOMMENDED | $57,880 | $82,390 |
$52,900
157,679
kWh
|
$(-6,220.0)
-
MMBtu
|
$560
-
gal
|
$1,060
-
gal
|
$9,580
-
lb
|
||
TOTAL IMPLEMENTED | $13,300 | $12,300 |
$2,100
90,270
kWh
|
- |
$560
-
gal
|
$1,060
-
gal
|
$9,580
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs