Assessment Year | 1995 |
---|---|
Principal Product | Recycling and densifying of plastics into granules |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 30 |
Plant Area |
60,125
ft2
|
Annual Production | 11,750
ton
|
Production Hrs. Annual | 6,384
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $153,215 | 1,747,655 |
kWh
|
$0.088 |
LPG | $18,626 | 2,440 |
MMBtu
|
$7.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,805 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,315 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,240 | - |
$13,240
-
kWh
|
- | |
02 | 2.3212: Optimize plant power factor | $19,120 | $23,550 |
$19,120
-
kWh
|
- | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,680 | - |
$3,680
70,926
kWh
|
- | |
04 | 2.7145: Install skylights | $1,180 | $2,550 |
$1,180
22,860
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $920 | $170 |
$920
10,258
kWh
|
- | |
06 | 2.8123: Pay utility bills on time | $753 | - | - | $753 | |
07 | 2.7124: Make a practice of turning off lights when not needed | $532 | $29 |
$532
7,327
kWh
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $230 | $328 |
$230
4,396
kWh
|
- | |
09 | 2.4314: Use synthetic lubricant | $150 | - |
$150
1,758
kWh
|
- | |
TOTAL RECOMMENDED | $39,805 | $26,627 |
$39,052
117,525
kWh
|
$753 | ||
TOTAL IMPLEMENTED | $24,315 | $23,907 |
$23,562
82,649
kWh
|
$753 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs