Assessment Year | 1991 |
---|---|
Principal Product | REMANUFACTURING OF CRANKSHAFTS |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
n/a
|
Annual Production | 313
pieces
|
Production Hrs. Annual | 8,650
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,606 | 1,072,685 |
kWh
|
$0.064 |
Natural Gas | $30,995 | 7,137 |
MMBtu
|
$4.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,905 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,905 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $2,330 | $6,532 | - |
$2,330
-
MMBtu
|
|
02 | 2.2511: Insulate bare equipment | $2,190 | $100 | - |
$2,190
-
MMBtu
|
|
03 | 2.2121: Increase amount of condensate returned | $870 | $715 | - |
$870
-
MMBtu
|
|
04 | 2.2437: Recover waste heat from equipment | $840 | $1,009 | - |
$840
-
MMBtu
|
|
05 | 2.2122: Install / repair insulation on condensate lines | $630 | $340 | - |
$630
-
MMBtu
|
|
06 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $440 | $315 |
$440
17,585
kWh
|
- | |
07 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $320 | - |
$320
13,189
kWh
|
- | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $165 | - |
$165
1,758
kWh
|
- | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $120 | $75 |
$120
4,982
kWh
|
- | |
TOTAL RECOMMENDED | $7,905 | $9,086 |
$1,045
37,514
kWh
|
$6,860
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,905 | $9,086 |
$1,045
37,514
kWh
|
$6,860
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs