Assessment Year | 1991 |
---|---|
Principal Product | STEEL POLES |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
n/a
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $84,276 | 1,823,857 |
kWh
|
$0.046 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,193 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|
01 | 2.3134: Shift from daytime to nighttime operation | $8,400 | $6,000 |
$14,400
-
kWh
|
$(-6,000.0) | |
02 | 2.3191: Use demand controller or load shedder | $9,000 | $12,500 |
$9,000
-
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,970 | $1,450 |
$4,720
206,917
kWh
|
$(-750.0) | |
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $2,640 | - |
$2,640
116,061
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,230 | $2,095 |
$810
16,706
kWh
|
$420 | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $390 | - |
$390
16,999
kWh
|
- | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $170 | $90 |
$170
7,620
kWh
|
- | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $330 | $190 |
$330
14,654
kWh
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $63 | $51 |
$63
1,758
kWh
|
- | |
TOTAL RECOMMENDED | $26,193 | $22,376 |
$32,523
380,715
kWh
|
$(-6,330.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs