ITAC Assessment: AM0111
ITAC logo
ITAC Assessment: AM0111
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product HOT MIX ASPHALT,CONCRETE
NAICS
n/a
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $1
M
to 5
M
# of Employees 19
Plant Area
n/a
Annual Production 125,000
ton
Production Hrs. Annual 1,300
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,110 586,166
kWh
Natural Gas $80,794 37,100
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,642 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,642

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $7,760 - $7,760
-
kWh
-
02 2.2511: Insulate bare equipment $6,300 $7,100 - $6,300
-
MMBtu
03 2.3212: Optimize plant power factor $3,530 $5,700 $3,530
-
kWh
-
04 2.2414: Use waste heat from hot flue gases to preheat $2,130 $5,540 $(-350.0)
(-5,862)
kWh
$2,480
-
MMBtu
05 2.2511: Insulate bare equipment $1,820 $4,800 - $1,820
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $102 $34 - $102
-
MMBtu
TOTAL RECOMMENDED $21,642 $23,174 $10,940
(-5,862)
kWh
$10,702
-
MMBtu
TOTAL IMPLEMENTED $21,642 $23,174 $10,940
(-5,862)
kWh
$10,702
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs