| Assessment Year | 1991 |
|---|---|
| Principal Product | HOT MIX ASPHALT,CONCRETE |
| NAICS |
n/a
|
| SIC | 2951: Asphalt Paving Mixtures and Blocks |
| Sales Range | $1 M to 5M |
| # of Employees | 19 |
| Plant Area |
n/a
|
| Annual Production | 125,000
ton
|
| Production Hrs. Annual | 1,300
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $62,110 | 586,166 |
kWh
|
$0.11 |
| Natural Gas | $80,794 | 37,100 |
MMBtu
|
$2.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,642 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,642 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,760 | - |
$7,760
-
kWh
|
- | |
| 02 | 2.2511: Insulate bare equipment | $6,300 | $7,100 | - |
$6,300
-
MMBtu
|
|
| 03 | 2.3212: Optimize plant power factor | $3,530 | $5,700 |
$3,530
-
kWh
|
- | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $2,130 | $5,540 |
$(-350.0)
(-5,862)
kWh
|
$2,480
-
MMBtu
|
|
| 05 | 2.2511: Insulate bare equipment | $1,820 | $4,800 | - |
$1,820
-
MMBtu
|
|
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $102 | $34 | - |
$102
-
MMBtu
|
|
| TOTAL RECOMMENDED | $21,642 | $23,174 |
$10,940
(-5,862)
kWh
|
$10,702
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $21,642 | $23,174 |
$10,940
(-5,862)
kWh
|
$10,702
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs