ITAC Assessment: AM0104
ITAC logo
ITAC Assessment: AM0104
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product HEAT EXCHANGERS
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area
n/a
Annual Production 250
pieces
Production Hrs. Annual 5,757
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,862 1,869,285
kWh
Natural Gas $42,016 8,371
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,439 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $5,160 $10,750 $(-390.0)
(-2,931)
kWh
$5,550
-
MMBtu
02 2.3212: Optimize plant power factor $4,050 $4,800 $4,050
-
kWh
-
03 2.2437: Recover waste heat from equipment $3,600 $1,800 - $3,600
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,100 $660 $3,100
93,787
kWh
-
05 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,900 $10,000 $2,900
87,925
kWh
-
06 2.6212: Turn off equipment during breaks, reduce operating time $1,400 - $1,400
42,790
kWh
-
07 2.7111: Reduce illumination to minimum necessary levels $1,100 $128 $1,100
19,050
kWh
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $129 $99 $129
1,465
kWh
-
TOTAL RECOMMENDED $21,439 $28,237 $12,289
242,086
kWh
$9,150
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs