ITAC Assessment: AM0090
ITAC logo
ITAC Assessment: AM0090
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product VITREOUS CHINA WARE
NAICS
n/a
SIC 3261: Vitreous China Plumbing Fixtures and China and Earthenware Fittings and Bathroom Accessories
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area
n/a
Annual Production 500,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $221,474 3,450,176
kWh
Natural Gas $399,208 148,950
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,426 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,371

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $18,200 $4,950 - $18,200
-
MMBtu
02 2.2428: Use flue gases in radiant heater for space heating, ovens, etc $5,635 $15,350 - $5,635
-
MMBtu
03 2.2511: Insulate bare equipment $625 $2,180 - $625
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $426 $300 $426
12,896
kWh
-
05 2.6212: Turn off equipment during breaks, reduce operating time $420 - $420
12,896
kWh
-
06 2.7111: Reduce illumination to minimum necessary levels $120 $120 $120
3,517
kWh
-
TOTAL RECOMMENDED $25,426 $22,900 $966
29,309
kWh
$24,460
-
MMBtu
TOTAL IMPLEMENTED $19,371 $7,550 $546
16,413
kWh
$18,825
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs