Assessment Year | 1990 |
---|---|
Principal Product | OIL FIELD EQUIPMENT |
NAICS |
n/a
|
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
n/a
|
Annual Production | 40
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $269,121 | 5,092,907 |
kWh
|
$0.053 |
Natural Gas | $82,011 | 17,164 |
MMBtu
|
$4.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,674 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,144 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,970 | $4,000 |
$10,970
-
kWh
|
- | - | |
02 | 2.6124: Establish equipment maintenance schedule | $13,250 | $4,000 | - | - | $13,250 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,560 | $7,000 |
$4,560
136,870
kWh
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $2,230 | $1,300 | - |
$2,230
-
MMBtu
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,150 | $2,220 |
$2,050
28,136
kWh
|
- | $100 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,300 | $4,956 |
$1,300
17,878
kWh
|
- | - | |
07 | 2.2443: Re-use or recycle hot or cold process exhaust air | $1,330 | $2,000 | - |
$1,330
-
MMBtu
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $184 | $76 |
$184
879
kWh
|
- | - | |
09 | 2.7111: Reduce illumination to minimum necessary levels | $700 | $200 |
$700
13,189
kWh
|
- | - | |
TOTAL RECOMMENDED | $36,674 | $25,752 |
$19,764
196,952
kWh
|
$3,560
-
MMBtu
|
$13,350 | ||
TOTAL IMPLEMENTED | $33,144 | $19,496 |
$18,464
179,074
kWh
|
$1,330
-
MMBtu
|
$13,350 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs