| Assessment Year | 1990 |
|---|---|
| Principal Product | HEAT EXCHANGERS |
| NAICS |
n/a
|
| SIC | 3433: Heating Equipment, Except Electric and Warm Air Furnaces |
| Sales Range | $10 M to 50M |
| # of Employees | 103 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $90,870 | 1,468,054 |
kWh
|
$0.062 |
| Natural Gas | $25,861 | 5,475 |
MMBtu
|
$4.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,601 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,601 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,390 | $2,000 |
$10,390
233,294
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,990 | $26,637 |
$5,990
115,475
kWh
|
- | |
| 03 | 2.2437: Recover waste heat from equipment | $2,440 | $2,000 | - |
$2,440
-
MMBtu
|
|
| 04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,670 | $4,050 |
$1,670
37,515
kWh
|
- | |
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $470 | - |
$470
10,551
kWh
|
- | |
| 06 | 2.6212: Turn off equipment during breaks, reduce operating time | $340 | - |
$340
7,620
kWh
|
- | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $255 | $90 |
$255
4,396
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $46 | $17 |
$46
586
kWh
|
- | |
| TOTAL RECOMMENDED | $21,601 | $34,794 |
$19,161
409,437
kWh
|
$2,440
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $21,601 | $34,794 |
$19,161
409,437
kWh
|
$2,440
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs