Assessment Year | 1988 |
---|---|
Principal Product | STORAGE TANKS & VESSELS |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $50 M to 100M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 28,000
ton
|
Production Hrs. Annual | 2,142
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $227,621 | 4,383,353 |
kWh
|
$0.052 |
Natural Gas | $30,488 | 6,541 |
MMBtu
|
$4.66 |
LPG | $10,000 | 470 |
MMBtu
|
$21.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,721 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,301 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,876 | - |
$10,876
-
kWh
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,301 | $1,500 |
$4,301
161,782
kWh
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $544 | $578 |
$544
9,086
kWh
|
|
TOTAL RECOMMENDED | $15,721 | $2,078 |
$15,721
170,868
kWh
|
||
TOTAL IMPLEMENTED | $4,301 | $1,500 |
$4,301
161,782
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs