Assessment Year | 1988 |
---|---|
Principal Product | WELDED WIRE FABRIC |
NAICS |
n/a
|
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 30,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,364 | 1,725,967 |
kWh
|
$0.062 |
Natural Gas | $2,791 | 678 |
MMBtu
|
$4.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,135 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,345 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $5,350 | $10,500 |
$5,350
-
kWh
|
|
02 | 2.4312: Improve lubrication practices | $1,470 | - |
$1,470
35,170
kWh
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,085 | $2,300 |
$1,085
18,171
kWh
|
|
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $970 | $600 |
$970
23,154
kWh
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $260 | - |
$260
6,155
kWh
|
|
TOTAL RECOMMENDED | $9,135 | $13,400 |
$9,135
82,650
kWh
|
||
TOTAL IMPLEMENTED | $1,345 | $2,300 |
$1,345
24,326
kWh
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs