| Assessment Year | 1988 |
|---|---|
| Principal Product | CATALYST CARRIERS |
| NAICS |
n/a
|
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
n/a
|
| Annual Production | 2,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $125,987 | 1,985,932 |
kWh
|
$0.063 |
| Natural Gas | $119,554 | 35,548 |
MMBtu
|
$3.36 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,346 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $3,578 | $300 |
$3,578
72,098
kWh
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $770 | $75 | - |
$770
-
MMBtu
|
|
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $8,426 | $17,000 | - |
$8,426
-
MMBtu
|
|
| 04 | 2.7261: Install timers and/or thermostats | $119 | $225 |
$76
1,758
kWh
|
$43
-
MMBtu
|
|
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $2,784 | $6,200 |
$2,784
47,773
kWh
|
- | |
| 06 | 2.4312: Improve lubrication practices | $920 | - |
$920
20,809
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $613 | $214 |
$613
9,086
kWh
|
- | |
| 08 | 2.8123: Pay utility bills on time | $1,018 | - |
$1,018
-
kWh
|
- | |
| 09 | 2.7261: Install timers and/or thermostats | $118 | $225 |
$118
2,052
kWh
|
- | |
| TOTAL RECOMMENDED | $18,346 | $24,239 |
$9,107
153,576
kWh
|
$9,239
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs