| Assessment Year | 1988 |
|---|---|
| Principal Product | REFRIGERATION COILS |
| NAICS |
n/a
|
| SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
| Sales Range | $5 M to 10M |
| # of Employees | 150 |
| Plant Area |
n/a
|
| Annual Production | 300,000
pieces
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $48,627 | 833,822 |
kWh
|
$0.058 |
| Natural Gas | $21,932 | 3,878 |
MMBtu
|
$5.66 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,116 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,261 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $3,075 | $6,920 | - |
$3,075
-
MMBtu
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,302 | $2,700 |
$1,302
35,170
kWh
|
- | |
| 03 | 2.2611: Moderate cooling tower outlet temperature | $945 | $550 |
$945
34,584
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $884 | $520 |
$884
32,239
kWh
|
- | |
| 05 | 2.4312: Improve lubrication practices | $476 | - |
$476
17,292
kWh
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $238 | - |
$238
8,792
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $137 | $319 |
$137
5,862
kWh
|
- | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $59 | $192 |
$59
2,345
kWh
|
- | |
| TOTAL RECOMMENDED | $7,116 | $11,201 |
$4,041
136,284
kWh
|
$3,075
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,261 | $10,140 |
$2,186
67,409
kWh
|
$3,075
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs