ITAC Assessment: AM0015
ITAC logo
ITAC Assessment: AM0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product CONCENTRATE FOR PLASTICS
NAICS
n/a
SIC 2865: Cyclic Organic Crudes and Intermediates, and Organic Dyes and Pigments
Sales Range $1
M
to 5
M
# of Employees 11
Plant Area
n/a
Annual Production 1,000,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,480 279,015
kWh
Natural Gas $1,639 260
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,590 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,599

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6218: Turn off equipment when not in use $2,599 - $2,599
72,978
kWh
02 2.2511: Insulate bare equipment $960 $2,000 $960
26,964
kWh
03 2.7111: Reduce illumination to minimum necessary levels $549 $2,040 $549
4,689
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $97 $33 $97
1,465
kWh
05 2.7261: Install timers and/or thermostats $136 $750 $136
4,689
kWh
06 2.4312: Improve lubrication practices $157 - $157
4,396
kWh
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $92 - $92
2,638
kWh
TOTAL RECOMMENDED $4,590 $4,823 $4,590
117,819
kWh
TOTAL IMPLEMENTED $2,599 - $2,599
72,978
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs