4,944
matching recommendations
$
$
ARC | 2+ Digits Required | |
NAICS | 3+ Digits Required | |
SIC | 2+ Digits Required | |
3+ Characters Required for Products |
ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
TT0339 #09 Y:2025 | 09 | 2025 | Reduce space conditioning during non-working hours | $868 | $100 |
n/a
|
TT0339 #08 Y:2025 | 08 | 2025 | Utilize energy-efficient belts and other improved mechanisms | $6,566 | $850 |
n/a
|
TT0339 #07 Y:2025 | 07 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $11,575 | $11,250 |
n/a
|
TT0339 #06 Y:2025 | 06 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $15,876 | $5,625 |
n/a
|
TT0339 #05 Y:2025 | 05 | 2025 | Turn off equipment during breaks, reduce operating time | $22,030 | $20,000 |
n/a
|
TT0339 #04 Y:2025 | 04 | 2025 | Utilize higher efficiency lamps and/or ballasts | $24,795 | $10,920 |
n/a
|
TT0339 #03 Y:2025 | 03 | 2025 | Optimize plant power factor | $31,076 | $9,750 |
n/a
|
TT0339 #02 Y:2025 | 02 | 2025 | Begin a practice of predictive / preventative maintenance | $33,333 | $35,000 |
n/a
|
TT0339 #01 Y:2025 | 01 | 2025 | Use solar heat for heat | $49,796 | $276,634 |
n/a
|
TT0336 #12 Y:2025 | 12 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $153 | $255 |
n/a
|
TT0336 #11 Y:2025 | 11 | 2025 | Install occupancy sensors | $355 | $1,600 |
n/a
|
TT0336 #10 Y:2025 | 10 | 2025 | Utilize controls to operate equipment only when needed | $507 | $100 |
n/a
|
TT0336 #09 Y:2025 | 09 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $551 | $375 |
n/a
|
TT0336 #08 Y:2025 | 08 | 2025 | Reduce the pressure of compressed air to the minimum required | $572 | $60 |
n/a
|
TT0336 #07 Y:2025 | 07 | 2025 | Eliminate or reduce compressed air usage | $1,078 | $400 |
n/a
|
TT0336 #06 Y:2025 | 06 | 2025 | Utilize controls to operate equipment only when needed | $1,830 | $500 |
n/a
|
TT0336 #05 Y:2025 | 05 | 2025 | Optimize plant power factor | $2,201 | $5,250 |
n/a
|
TT0336 #04 Y:2025 | 04 | 2025 | Burn a less expensive grade of fuel | $6,724 | $40,000 |
n/a
|
TT0336 #03 Y:2025 | 03 | 2025 | Reschedule plant operations or reduce load to avoid peaks | $13,640 | $6,680 |
n/a
|
TT0336 #02 Y:2025 | 02 | 2025 | Use battery storage for demand control | $19,703 | $159,000 |
n/a
|