Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

202

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Hardwood veneer and plywood manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UA0260 #06 Y:2022 Utilize energy-efficient belts and other improved mechanisms $5,000 $1,784
UA0260 #05 Y:2022 Optimize plant power factor $90,617 $35,347
UA0260 #04 Y:2022 Preheat combustion air with waste heat $230,787 $328,350
UA0260 #03 Y:2022 Use waste heat to produce steam to drive a steam turbine-generator $429,299 $2,825,211
UA0260 #02 Y:2022 Replace hydraulic / pneumatic equipment with electric equipment $3,710 $1,651
UA0260 #01 Y:2022 Eliminate or reduce compressed air usage $19,881 $1,000
OR0750 #06 Y:2022 Optimize plant power factor $49,792 $155,954
OR0750 #05 Y:2022 Eliminate leaks in inert gas and compressed air lines/ valves $87,087 $87,086
OR0750 #04 Y:2022 Increase use of automation $149,543 $65,909
OR0750 #03 Y:2022 Use / purchase optimum sized compressor $32,591 $4,338
OR0750 #02 Y:2022 Utilize energy-efficient belts and other improved mechanisms $1,128 -
OR0750 #01 Y:2022 Reduce the pressure of compressed air to the minimum required $8,607 -
OR0728 #04 Y:2019 Utilize energy-efficient belts and other improved mechanisms $4,008 -
OR0728 #03 Y:2019 Use or replace with energy efficient substitutes $8,174 $4,152
OR0728 #02 Y:2019 Install motor voltage controller on lightly loaded motors $29,427 $34,054
OR0728 #01 Y:2019 Reduce the pressure of compressed air to the minimum required $29,023 $34,574
IP0120 #09 Y:2019 Utilize energy-efficient belts and other improved mechanisms $691 $3,215
IP0120 #08 Y:2019 Use adjustable frequency drive or multiple speed motors on existing system $4,278 $7,549
IP0120 #07 Y:2019 Utilize higher efficiency lamps and/or ballasts $4,019 $4,963
IP0120 #06 Y:2019 Optimize plant power factor $9,284 $11,128