The Assessment Recommendation Codes ARC is the ITAC system for classifying recommendation types.
ARC | 2+ Digits Required | |
NAICS | 3+ Digits Required | |
SIC | 2+ Digits Required | |
3+ Characters Required for Products |
See the Assessment Recommendation Codes ARC Manual for additional details.
TOP
|
ARC | Description | Recommendations Rec's | Recommended Rec'd $ Savings | Average Avg Payback PB | Implementation Imp Rate |
---|---|---|---|---|---|---|
back
|
4.xxx | 4.xxx: DIRECT PRODUCTIVITY ENHANCEMENTS | 6.6k6,648 | $102k$102,342 avg | 1.0 yrs | 43.0% |
back
|
4.6xx | 4.6xx: Reduction of Downtime | 1.4k1,421 | $94k$93,623 avg | 1.0 yrs | 47.8% |
selected | 4.62x | 4.62x: Quick Change | 178178 | $127k$126,846 avg | 0.6 yrs | 51.8% |
4.621 | 4.621: USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | 5858 | $99k$99,433 avg | 0.8 yrs | 50.0% | |
4.622 | 4.622: INSTALL ROTATING CAROUSELS TO REDUCE SET-UP TIMES | 44 | $38k$37,807 avg | 1.1 yrs | 50.0% | |
4.623 | 4.623: EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME | 1919 | $67k$67,326 avg | 0.7 yrs | 36.8% | |
4.624 | 4.624: HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME | 1818 | $105k$105,268 avg | 1.2 yrs | 56.3% | |
4.625 | 4.625: DEVELOP STANDARD OPERATING PROCEDURES | 7979 | $171k$170,711 avg | 0.3 yrs | 56.2% |