Assessment Year | 2000 |
---|---|
Principal Product | Aircraft servicing |
NAICS |
n/a
|
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
144,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,945 | 3,371,630 |
kWh
|
$0.052 |
Electricity Fees | $8,134 | - |
|
- |
Natural Gas | $67,034 | 10,150 |
MMBtu
|
$6.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $87,271 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,380 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,345 | $1,188 |
$1,345
9,672
kWh
|
- | - | - | |
02 | 2.7122: Disconnect ballasts | $35,158 | $3,925 |
$35,158
650,938
kWh
|
- | - | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $7,637 | $8,440 | - |
$7,637
-
MMBtu
|
- | - | |
04 | 2.1113: Reduce combustion air flow to optimum | $9,700 | $1,000 | - |
$9,700
-
MMBtu
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $602 | $50 |
$602
11,137
kWh
|
- | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $950 | $200 |
$950
17,585
kWh
|
- | - | - | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,846 | $10,000 | - | - |
$9,846
-
lb
|
- | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,824 | $350 | - | - |
$1,824
-
lb
|
- | |
09 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,209 | $11,000 | - | - |
$5,209
-
lb
|
- | |
10 | 4.111: Add equipment/ operators to reduce production bottleneck | $15,000 | $1,500 | - | - | - | $15,000 | |
TOTAL RECOMMENDED | $87,271 | $37,653 |
$38,055
689,332
kWh
|
$17,337
-
MMBtu
|
$16,879
-
lb
|
$15,000 | ||
TOTAL IMPLEMENTED | $48,380 | $14,525 |
$36,710
679,660
kWh
|
- |
$11,670
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs