Assessment Year | 2024 |
---|---|
Principal Product | Aircraft Engine |
NAICS | 336412: Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $1 M to 5M |
# of Employees | 50 |
Plant Area |
75,000
ft2
|
Annual Production | 1,000
ton
|
Production Hrs. Annual | 2,875
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $57,089 | 780,680 |
kWh
|
$0.073 | |
Electricity Demand | $34,896 | 1,946 |
kW-mo/yr
|
$17.93 | |
Electricity Fees | $11,428 | - |
|
- | |
Natural Gas | $24,460 | 2,793 |
MMBtu
|
$8.76 | |
Fuel Oil #1 | $22,660 | 1,000 |
MMBtu
|
$22.66 | |
Waste Disposal Costs | |||||
Water Usage | $9,497 | 1,801 |
Tgal
|
$5.27 | |
Water Disposal | $10,438 | 1,801 |
Tgal
|
$5.79 | |
TOTAL YEARLY COSTS | $170,468 | ||||
RECOMMENDED SAVINGS* | $28,992 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $13,280 | - |
$4,725
64,723
kWh
|
- |
$8,555
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,591 | $9,372 |
$4,242
58,107
kWh
|
$3,349
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $3,845 | - |
$2,149
29,438
kWh
|
$1,696
-
kW-mo/yr
|
- | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $2,436 | - |
$1,051
14,403
kWh
|
$351
-
kW-mo/yr
|
$1,033
-
MMBtu
|
|
05 | 2.7241: Install outside air damper / economizer on hvac unit | $1,454 | $2,360 |
$1,454
19,917
kWh
|
- | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $386 | $677 |
$386
5,292
kWh
|
- | - | |
TOTAL RECOMMENDED | $28,992 | $12,409 |
$14,007
191,880
kWh
|
$5,397
-
kW-mo/yr
|
$9,588
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs