ITAC Assessment: WI0430
ITAC logo
ITAC Assessment: WI0430
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Currugated Boxes
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 200,000
ft2
Annual Production 1,100,000,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,466 4,859,250
kWh
Electricity Demand $84,234 10,789
kW-mo/yr
Electricity Fees $45,897 -
Natural Gas $481,174 62,790
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,415 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,430

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $24,059 $25,000 - - $24,059
-
MMBtu
02 2.7135: Install occupancy sensors $6,072 $18,000 n/a $3,867
134,280
kWh
$2,205
-
kW-mo/yr
-
03 2.2414: Use waste heat from hot flue gases to preheat $4,938 $11,250 n/a - - $4,938
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,916 $1,549 $1,260
43,765
kWh
$656
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $741 - $471
16,365
kWh
$270
-
kW-mo/yr
-
06 2.2136: Install / repair insulation on steam lines $689 $39 - - $689
-
MMBtu
TOTAL RECOMMENDED $38,415 $55,838 $5,598
194,410
kWh
$3,131
-
kW-mo/yr
$29,686
-
MMBtu
TOTAL IMPLEMENTED $1,430 $39 $471
16,365
kWh
$270
-
kW-mo/yr
$689
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs