Assessment Year | 1988 |
---|---|
Principal Product | COMPRESSED GAS CYLINDERS |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 132 |
Plant Area |
n/a
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 4,200
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $306,097 | 4,769,050 |
kWh
|
$0.064 |
Natural Gas | $336,070 | 112,975 |
MMBtu
|
$2.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,285 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,456 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $31,106 | - |
$31,106
484,760
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,304 | - |
$1,304
20,223
kWh
|
- | - | |
03 | 2.3132: Recharge batteries on during off-peak demand periods | $912 | - |
$912
-
kWh
|
- | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,240 | - |
$4,080
-
kWh
|
- | $(-840.0) | |
05 | 2.2437: Recover waste heat from equipment | $5,542 | $3,000 | - |
$5,542
-
MMBtu
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,181 | $500 | - |
$5,481
-
MMBtu
|
$(-300.0) | |
TOTAL RECOMMENDED | $47,285 | $3,500 |
$37,402
504,983
kWh
|
$11,023
-
MMBtu
|
$(-1,140.0) | ||
TOTAL IMPLEMENTED | $5,456 | - |
$6,296
20,223
kWh
|
- | $(-840.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs