Assessment Year | 2024 |
---|---|
Principal Product | Sewage Treatment Facilities |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 15 |
Plant Area |
156,234
ft2
|
Annual Production | 400
ton
|
Production Hrs. Annual | 4,928
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $122,120 | 3,625,552 |
kWh
|
$0.034 |
Fuel Oil #1 | $11,303 | 331 |
MMBtu
|
$34.15 |
TOTAL YEARLY COSTS | $133,423 | |||
RECOMMENDED SAVINGS* | $7,988 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #1 Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $177 | $715 |
$27
809
kWh
|
- | $150 | - | |
02 | 2.4134: Replace electric motor with fossil fuel engine | $5,536 | - |
$(-116.0)
(-3,446)
kWh
|
$5,652
-
MMBtu
|
- | - | |
03 | 2.4321: Upgrade obsolete equipment | $2,275 | - | - |
$5,652
-
MMBtu
|
- | $(-3,377.0) | |
TOTAL RECOMMENDED | $7,988 | $715 |
$(-89.0)
(-2,637)
kWh
|
$11,304
-
MMBtu
|
$150 | $(-3,377.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs