Assessment Year | 2024 |
---|---|
Principal Product | Other Aircraft Parts and Auxiliary Equipment Manufacturing |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 334 |
Plant Area |
79,000
ft2
|
Annual Production | 2,500
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $197,319 | 2,569,289 |
kWh
|
$0.077 |
Electricity Demand | $60,964 | 6,024 |
kW-mo/yr
|
$10.12 |
Electricity Fees | $39,292 | - |
|
- |
Natural Gas | $104,262 | 9,905 |
MMBtu
|
$10.53 |
TOTAL YEARLY COSTS | $401,837 | |||
RECOMMENDED SAVINGS* | $195,856 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,834 | $25,000 |
$14,263
185,712
kWh
|
$2,571
-
kW-mo/yr
|
- | - | |
02 | 2.6127: Maintain air filters by cleaning or replacement | $4,277 | $12,000 |
$3,623
47,178
kWh
|
$654
-
kW-mo/yr
|
- | - | |
03 | 2.2511: Insulate bare equipment | $24,745 | $24,732 | - | - |
$24,745
-
MMBtu
|
- | |
04 | 4.432: Cross-train personnel to avoid lost time | $150,000 | $200,000 | - | - | - | $150,000 | |
TOTAL RECOMMENDED | $195,856 | $261,732 |
$17,886
232,890
kWh
|
$3,225
-
kW-mo/yr
|
$24,745
-
MMBtu
|
$150,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs