Assessment Year | 2025 |
---|---|
Principal Product | Mineral Ore Solutions |
NAICS | 325110: Petrochemical Manufacturing |
SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 26 |
Plant Area |
25,000
ft2
|
Annual Production | 400
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $13,733 | 359,281 |
kWh
|
$0.038 | |
Electricity Demand | $9,897 | 947 |
kW-mo/yr
|
$10.45 | |
Electricity Fees | $11,203 | - |
|
- | |
LPG | $151,900 | 6,832 |
MMBtu
|
$22.23 | |
Waste Disposal Costs | |||||
Water Usage | $8,156 | 1,693 |
Tgal
|
$4.82 | |
TOTAL YEARLY COSTS | $194,889 | ||||
RECOMMENDED SAVINGS* | $858,546 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | LPG Savings | Administrative Changes Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2444: Use hot process fluids to preheat incoming process fluids | $25,676 | $9,660 |
$25,676
-
MMBtu
|
- | - | - | - | |
02 | 2.1331: Burn a less expensive grade of fuel | $101,028 | $4,860 | - | - | - | $101,028 | - | |
03 | 2.2136: Install / repair insulation on steam lines | $8,514 | $6,920 |
$8,514
-
MMBtu
|
- | - | - | - | |
04 | 2.2121: Increase amount of condensate returned | $31,296 | $7,800 |
$28,899
-
MMBtu
|
$(-2,192.0) |
$4,589
-
Tgal
|
- | - | |
05 | 2.1332: Convert combustion equipment to burn natural gas | $11,222 | $30,630 | - | - | - | $11,222 | - | |
06 | 2.2211: Use optimum temperature | $680,810 | $2,017,330 | - | - | - | - | $680,810 | |
TOTAL RECOMMENDED | $858,546 | $2,077,200 |
$63,089
-
MMBtu
|
$(-2,192.0) |
$4,589
-
Tgal
|
$112,250 | $680,810 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | LPG Savings | Administrative Changes Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs