Assessment Year | 2021 |
---|---|
Principal Product | Fiberglass Insulation |
NAICS | 327211: Flat Glass Manufacturing |
SIC | 3211: Flat Glass |
Sales Range | $10 M to 50M |
# of Employees | 41 |
Plant Area |
300,000
ft2
|
Annual Production | 74,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,286,699 | 39,148,800 |
kWh
|
$0.033 | |
Electricity Demand | $824,761 | 60,040 |
kW-mo/yr
|
$13.74 | |
Natural Gas | $375,950 | 91,671 |
MMBtu
|
$4.10 | |
Waste Disposal Costs | |||||
Water Usage | $20,646 | 17,145 |
Tgal
|
$1.20 | |
TOTAL YEARLY COSTS | $2,508,057 | ||||
RECOMMENDED SAVINGS* | $79,392 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $59,220 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,862 | $88,688 |
$17,399
528,844
kWh
|
$9,463
-
kW-mo/yr
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $22,604 | $16,880 |
$14,383
437,176
kWh
|
$8,221
-
kW-mo/yr
|
|
03 | 2.2511: Insulate bare equipment | $20,172 | $4,900 |
$12,922
391,580
kWh
|
$7,249
-
kW-mo/yr
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,017 | $14,979 |
$5,101
155,052
kWh
|
$2,916
-
kW-mo/yr
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,737 | $860 |
$1,105
33,590
kWh
|
$632
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $79,392 | $126,307 |
$50,910
1,546,242
kWh
|
$28,481
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $59,220 | $121,407 |
$37,988
1,154,662
kWh
|
$21,232
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs