| Assessment Year | 2006 |
|---|---|
| Principal Product | Medica C-Arms |
| NAICS | 334517: Irradiation Apparatus Manufacturing |
| SIC | 3844: X-Ray Apparatus and Tubes and Related Irradiation Apparatus |
| Sales Range | $100 M to 500M |
| # of Employees | 440 |
| Plant Area |
185,000
ft2
|
| Annual Production | 5,300
pieces
|
| Production Hrs. Annual | 4,198
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $108,616 | 4,154,820 |
kWh
|
$0.026 |
| Electricity Demand | $116,656 | 10,421 |
kW-mo/yr
|
$11.19 |
| Natural Gas | $26,323 | 3,742 |
MMBtu
|
$7.03 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $67,320 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $1,800 | $2,220 | - |
$1,800
-
kW-mo/yr
|
- | |
| 02 | 2.3191: Use demand controller or load shedder | $24,880 | $20,000 | - |
$24,880
-
kW-mo/yr
|
- | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $3,730 | $970 |
$2,570
85,872
kWh
|
$1,160
-
kW-mo/yr
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,040 | $90 |
$300
9,990
kWh
|
$740
-
kW-mo/yr
|
- | |
| 05 | 2.6218: Turn off equipment when not in use | $3,360 | $2,960 |
$3,360
112,200
kWh
|
- | - | |
| 06 | 2.7233: Use properly designed and sized hvac equipment | $32,510 | $249,000 |
$20,870
696,690
kWh
|
- | $11,640 | |
| TOTAL RECOMMENDED | $67,320 | $275,240 |
$27,100
904,752
kWh
|
$28,580
-
kW-mo/yr
|
$11,640 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs