Assessment Year | 2004 |
---|---|
Principal Product | boxes |
NAICS | 322212: Folding Paperboard Box Manufacturing |
SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
Sales Range | $10 M to 50M |
# of Employees | 206 |
Plant Area |
180,190
ft2
|
Annual Production | 50,000,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $80,858 | 2,839,886 |
kWh
|
$0.028 |
Electricity Demand | $98,504 | 12,477 |
kW-mo/yr
|
$7.89 |
Electricity Fees | $31,490 | - |
|
- |
Natural Gas | $40,708 | 7,531 |
MMBtu
|
$5.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,525,408 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,404 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $12,920 | $20,250 | - | - | $12,920 | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,404 | $790 |
$650
21,600
kWh
|
$754
-
kW-mo/yr
|
- | - | |
03 | 2.7144: Install spectral reflectors / delamp | $380 | $280 |
$200
6,600
kWh
|
$180
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $392 | $1,990 |
$146
4,800
kWh
|
$246
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $1,690 | $3,226 |
$726
23,800
kWh
|
$964
-
kW-mo/yr
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $262 | $440 |
$262
8,600
kWh
|
- | - | - | |
07 | 4.512: Condense operation into one building | $2,508,360 | $6,420,700 | - | - | - | $2,508,360 | |
TOTAL RECOMMENDED | $2,525,408 | $6,447,676 |
$1,984
65,400
kWh
|
$2,144
-
kW-mo/yr
|
$12,920 | $2,508,360 | ||
TOTAL IMPLEMENTED | $1,404 | $790 |
$650
21,600
kWh
|
$754
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs