ITAC Assessment: UMS013
ITAC logo
ITAC Assessment: UMS013
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Molten aluminum
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3354: Aluminum Extruded Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 100,000
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $747,267 7,472,670
kWh
Natural Gas $2,804,008 547,063
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,701,000 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $320,000 $600,000 - $320,000
-
MMBtu
02 2.1213: Direct warmest air to combustion intake $106,000 $200,000 - $106,000
-
MMBtu
03 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust $673,000 $1,000,000 $673,000
6,750,000
kWh
-
04 2.2414: Use waste heat from hot flue gases to preheat $465,000 $700,000 - $465,000
-
MMBtu
05 2.1233: Analyze flue gas for proper air/fuel ratio $137,000 - - $137,000
-
MMBtu
TOTAL RECOMMENDED $1,701,000 $2,500,000 $673,000
6,750,000
kWh
$1,028,000
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs