ITAC Assessment: UM0481
ITAC logo
ITAC Assessment: UM0481
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Customized, un-cured, bulk silicone elastomer
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 80
Plant Area 94,600
ft2
Annual Production 25,353,160
lb
Production Hrs. Annual 8,544
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $387,757 3,953,370
kWh
Natural Gas $25,360 4,053
MMBtu
TOTAL YEARLY COSTS $413,117
RECOMMENDED SAVINGS* $98,929 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Primary Raw Material Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $7,978 $3,000 $11,239
114,683
kWh
$(-3,260.8)
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $21,854 $34,336 $21,854
222,998
kWh
- -
03 2.7135: Install occupancy sensors $18,599 $6,600 $18,599
189,784
kWh
- -
04 2.1336: Install equipment to utilize waste fuel $50,498 $100,000 - - $50,498
TOTAL RECOMMENDED $98,929 $143,936 $51,692
527,465
kWh
$(-3,260.8)
-
MMBtu
$50,498
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs