ITAC Assessment: UM0355
ITAC logo
ITAC Assessment: UM0355
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Books and Book Bindings
NAICS 323117: Books Printing
SIC 2732: Book Printing
Sales Range $10
M
to 50
M
# of Employees 258
Plant Area 164,000
ft2
Annual Production 14,000,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $255,509 5,990,600
kWh
Electricity Demand $212,109 13,022
kW-mo/yr
Natural Gas $18,285 1,634
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,861 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,234

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3132: Recharge batteries on during off-peak demand periods $6,255 $18,000 - $6,255
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,008 $8,286 $2,293
53,894
kWh
$2,715
-
kW-mo/yr
-
03 2.7221: Lower temperature during the winter season and vice-versa $2,372 $500 - - $2,372
-
MMBtu
04 2.7313: Recycle air for heating, ventilation and air conditioning $2,314 $500 - - $2,314
-
MMBtu
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $912 $912 $545
12,780
kWh
$367
-
kW-mo/yr
-
TOTAL RECOMMENDED $16,861 $28,198 $2,838
66,674
kWh
$9,337
-
kW-mo/yr
$4,686
-
MMBtu
TOTAL IMPLEMENTED $8,234 $9,698 $2,838
66,674
kWh
$3,082
-
kW-mo/yr
$2,314
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs