ITAC Assessment: UM0237
ITAC logo
ITAC Assessment: UM0237
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Industrial Lubricants
NAICS 324191: Petroleum Lubricating Oil and Grease Manufacturing
SIC 2992: Lubricating Oils and Greases
Sales Range $10
M
to 50
M
# of Employees 26
Plant Area 78,000
ft2
Annual Production 16,000,000
lb
Production Hrs. Annual 4,810
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $160,937 1,697,646
kWh
Electricity Fees $1,294 -
Natural Gas $26,919 4,168
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $140,822 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,396

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Primary Product Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $116,280 $1,500 - - $116,280
02 2.2522: Isolate hot or cold equipment $11,459 $10,000 $11,459
119,360
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,000 $2,498 $5,000
51,862
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,937 $1,650 $3,937
41,014
kWh
- -
05 2.7243: Improve air circulation with destratification fans / other methods $4,146 $2,100 - $4,146
-
MMBtu
-
TOTAL RECOMMENDED $140,822 $17,748 $20,396
212,236
kWh
$4,146
-
MMBtu
$116,280
TOTAL IMPLEMENTED $15,396 $11,650 $15,396
160,374
kWh
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs