| Assessment Year | 2025 |
|---|---|
| Principal Product | Thermoplastic Resins |
| NAICS | 325211: Plastics Material and Resin Manufacturing |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $50 M to 100M |
| # of Employees | 105 |
| Plant Area |
210,000
ft2
|
| Annual Production | 10,660
ton
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $441,213 | 15,713,600 |
kWh
|
$0.028 |
| Electricity Demand | $654,795 | 34,997 |
kW-mo/yr
|
$18.71 |
| Electricity Fees | $104,024 | - |
|
- |
| Natural Gas | $521,928 | 252,045 |
MMBtu
|
$2.07 |
| TOTAL YEARLY COSTS | $1,721,960 | |||
| RECOMMENDED SAVINGS* | $192,001 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $77,396 | $40,000 | - | - | - |
$77,396
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,455 | $2,940 |
$4,455
158,539
kWh
|
- | - | - | |
| 03 | 2.2692: Use outside cold water source as a supply of cooling water | $43,343 | $86,469 |
$22,731
803,796
kWh
|
$20,612
-
kW-mo/yr
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $49,775 | $25,480 | - | - | $49,775 | - | |
| 05 | 2.9114: Use solar heat to make electricty | $13,709 | $151,700 |
$6,345
225,990
kWh
|
$7,364
-
kW-mo/yr
|
- | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,323 | $17,116 |
$3,323
118,330
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $192,001 | $323,705 |
$36,854
1,306,655
kWh
|
$27,976
-
kW-mo/yr
|
$49,775 |
$77,396
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs