ITAC Assessment: UL2502
ITAC logo
ITAC Assessment: UL2502
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Tarps and Tents
NAICS 423990: Other Miscellaneous Durable Goods Merchant Wholesalers
SIC 5099: Durable Goods, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 275
Plant Area 275,000
ft2
Annual Production 100,000
units
Production Hrs. Annual 2,080
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,269 1,142,912
kWh
Electricity Demand $141,664 5,813
kW-mo/yr
Electricity Fees $34,134 -
Natural Gas $36,012 1,603
MMBtu
TOTAL YEARLY COSTS $271,078
RECOMMENDED SAVINGS* $98,525 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,810 $630 $7,810
150,607
kWh
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,066 - $1,066
20,534
kWh
- - -
03 2.3212: Optimize plant power factor $2,331 $7,280 - - $2,331 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $94 $35 $40
774
kWh
$54
-
kW-mo/yr
- -
05 2.7135: Install occupancy sensors $753 $155 $753
14,524
kWh
- - -
06 2.7111: Reduce illumination to minimum necessary levels $3,639 - $1,545
29,786
kWh
$2,094
-
kW-mo/yr
- -
07 2.9114: Use solar heat to make electricty $74,556 $570,771 $38,466
741,758
kWh
$36,090
-
kW-mo/yr
- -
08 2.7226: Use computer programs to optimize hvac performance $8,276 $1,800 $2,279
43,946
kWh
- - $5,997
-
MMBtu
TOTAL RECOMMENDED $98,525 $580,671 $51,959
1,001,929
kWh
$38,238
-
kW-mo/yr
$2,331 $5,997
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs