ITAC Assessment: UL2317
ITAC logo
ITAC Assessment: UL2317
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Rubber Shock Absorbers for Vibrating Equipment
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3061: Molded, Extruded, and Lathe-Cut Mechanical Rubber Goods
Sales Range $10
M
to 50
M
# of Employees 324
Plant Area 237,500
ft2
Annual Production 47,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $422,905 11,980,800
kWh
Electricity Demand $487,079 22,754
kW-mo/yr
Electricity Fees $135,044 -
Natural Gas $638,008 60,278
MMBtu
TOTAL YEARLY COSTS $1,683,036
RECOMMENDED SAVINGS* $33,805 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.9114: Use solar heat to make electricty $16,039 $148,666 $7,782
220,460
kWh
$8,257
-
kW-mo/yr
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $6,159 - $6,159
174,494
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,022 $2,077 $492
13,937
kWh
$1,530
-
kW-mo/yr
-
04 2.7144: Install spectral reflectors / delamp $2,720 $500 $1,256
35,568
kWh
$1,464
-
kW-mo/yr
-
05 2.3212: Optimize plant power factor $6,865 $9,100 - - $6,865
TOTAL RECOMMENDED $33,805 $160,343 $15,689
444,459
kWh
$11,251
-
kW-mo/yr
$6,865
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs