ITAC Assessment: UL0151
ITAC logo
ITAC Assessment: UL0151
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Automative Exhaust Systems
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 90,000
ft2
Annual Production 800,000
pieces
Production Hrs. Annual 6,624
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,543 6,249,121
kWh
Electricity Demand $96,145 13,799
kW-mo/yr
Electricity Fees $2,136 -
Natural Gas $63,873 19,362
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $523,089 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,589

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings By-product Production Savings
01 2.4133: Use most efficient type of electric motors $297 $2,900 $185
8,792
kWh
$112
-
kW-mo/yr
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $692 $20 $343
16,413
kWh
$349
-
kW-mo/yr
- - -
03 3.5311: Recover and reuse waste material $517,500 $1,800 - - - $(-172,500.0) $690,000
04 3.5315: Lease / purchase baler; sell cardboard to recycler $3,275 - - - $3,275
-
lb
- -
05 3.5316: Contract a wood pallet recycling company $1,325 - - - $1,325
-
lb
- -
TOTAL RECOMMENDED $523,089 $4,720 $528
25,205
kWh
$461
-
kW-mo/yr
$4,600
-
lb
$(-172,500.0) $690,000
TOTAL IMPLEMENTED $5,589 $2,920 $528
25,205
kWh
$461
-
kW-mo/yr
$4,600
-
lb
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs