Assessment Year | 1996 |
---|---|
Principal Product | Automative Exhaust Systems |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
85,000
ft2
|
Annual Production | 320,000
pieces
|
Production Hrs. Annual | 6,624
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $125,424 | 6,004,103 |
kWh
|
$0.021 |
Electricity Demand | $92,375 | 13,258 |
kW-mo/yr
|
$6.97 |
Electricity Fees | $2,052 | - |
|
- |
Natural Gas | $61,368 | 18,603 |
MMBtu
|
$3.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $210,289 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $35,289 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $27,420 | $2,000 | - | - |
$27,420
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $964 | $921 |
$588
28,136
kWh
|
$376
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $2,555 | $4,500 |
$1,592
76,202
kWh
|
$963
-
kW-mo/yr
|
- | - | |
04 | 3.5311: Recover and reuse waste material | $175,000 | $1,800 | - | - | - |
$175,000
-
lb
|
|
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,825 | - | - | - | - |
$2,825
-
lb
|
|
06 | 3.5316: Contract a wood pallet recycling company | $1,525 | - | - | - | - |
$1,525
-
lb
|
|
TOTAL RECOMMENDED | $210,289 | $9,221 |
$2,180
104,338
kWh
|
$1,339
-
kW-mo/yr
|
$27,420
-
MMBtu
|
$179,350
-
lb
|
||
TOTAL IMPLEMENTED | $35,289 | $7,421 |
$2,180
104,338
kWh
|
$1,339
-
kW-mo/yr
|
$27,420
-
MMBtu
|
$4,350
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs