ITAC Assessment: UL0150
ITAC logo
ITAC Assessment: UL0150
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Automative Exhaust Systems
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 85,000
ft2
Annual Production 320,000
pieces
Production Hrs. Annual 6,624
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,424 6,004,103
kWh
Electricity Demand $92,375 13,258
kW-mo/yr
Electricity Fees $2,052 -
Natural Gas $61,368 18,603
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $210,289 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $35,289

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $27,420 $2,000 - - $27,420
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $964 $921 $588
28,136
kWh
$376
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $2,555 $4,500 $1,592
76,202
kWh
$963
-
kW-mo/yr
- -
04 3.5311: Recover and reuse waste material $175,000 $1,800 - - - $175,000
-
lb
05 3.5315: Lease / purchase baler; sell cardboard to recycler $2,825 - - - - $2,825
-
lb
06 3.5316: Contract a wood pallet recycling company $1,525 - - - - $1,525
-
lb
TOTAL RECOMMENDED $210,289 $9,221 $2,180
104,338
kWh
$1,339
-
kW-mo/yr
$27,420
-
MMBtu
$179,350
-
lb
TOTAL IMPLEMENTED $35,289 $7,421 $2,180
104,338
kWh
$1,339
-
kW-mo/yr
$27,420
-
MMBtu
$4,350
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs