ITAC Assessment: UL0110
ITAC logo
ITAC Assessment: UL0110
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Injection molded platics
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 1,047
Plant Area 450,000
ft2
Annual Production 80,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $369,136 10,405,334
kWh
Natural Gas $89,509 25,961
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,136 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $7,563 $15,800 n/a $7,563
175,850
kWh
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,502 $2,161 n/a $1,502
34,877
kWh
03 2.2511: Insulate bare equipment $1,017 $205 n/a $1,017
23,740
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,054 $10,016 n/a $5,054
142,438
kWh
TOTAL RECOMMENDED $15,136 $28,182 $15,136
376,905
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs