| Assessment Year | 2021 |
|---|---|
| Principal Product | Wastewater Treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 12 |
| Plant Area |
42,350
ft2
|
| Annual Production | 685,400
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $151,174 | 3,220,200 |
kWh
|
$0.047 |
| Electricity Demand | $33,179 | 5,673 |
kW-mo/yr
|
$5.85 |
| Electricity Fees | $22,114 | - |
|
- |
| TOTAL YEARLY COSTS | $206,467 | |||
| RECOMMENDED SAVINGS* | $481,813 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,921 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,527 | $41,169 |
$9,527
202,629
kWh
|
- | - | - | - | - | - | - | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $6,690 | $2,000 |
$6,690
142,337
kWh
|
- | - | - | - | - | - | - | |
| 03 | 2.4112: Install soft-start to eliminate nuisance trips | $5,976 | $16,642 |
$5,976
127,155
kWh
|
- | - | - | - | - | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,332 | - |
$2,015
42,872
kWh
|
- | - | - | $154 | $163 | - | - | |
| 05 | 3.5217: Reuse / recycle/ sell paper products | $450,043 | $53,000 |
$(-10,851.0)
(-230,868)
kWh
|
$(-2,548.0)
-
kW-mo/yr
|
$(-18,095.0)
-
MMBtu
|
- | - | - | - | $481,537 | |
| 06 | 3.6192: Use a less expensive method of waste removal | $4,159 | $4,000 | - | - | - | - | $4,159 | - | - | - | |
| 07 | 3.4151: Minimize water usage | $1,899 | - | - | - | - |
$1,899
-
Tgal
|
- | - | - | - | |
| 08 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $1,187 | - | - | - | - | - | - | - | $1,187 | - | |
| TOTAL RECOMMENDED | $481,813 | $116,811 |
$13,357
284,125
kWh
|
$(-2,548.0)
-
kW-mo/yr
|
$(-18,095.0)
-
MMBtu
|
$1,899
-
Tgal
|
$4,313 | $163 | $1,187 | $481,537 | ||
| TOTAL IMPLEMENTED | $20,921 | $57,811 |
$17,518
372,656
kWh
|
- | - |
$1,899
-
Tgal
|
$154 | $163 | $1,187 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs