Assessment Year | 2006 |
---|---|
Principal Product | Corrugated board containers |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | n/a |
# of Employees | 120 |
Plant Area |
294,000
ft2
|
Annual Production | 1,000,000,000
units
|
Production Hrs. Annual | 6,656
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $722,095 | 846,151 |
kWh
|
$0.85 |
Electricity Demand | $132,163 | 17,283 |
kW-mo/yr
|
$7.65 |
Natural Gas | $1,009,694 | 89,507 |
MMBtu
|
$11.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $239,557 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,671 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4323: Use optimum size and capacity equipment | $24,522 | $41,500 |
$21,714
133,563
kWh
|
$2,808
-
kW-mo/yr
|
- | - | - | |
02 | 2.6218: Turn off equipment when not in use | $2,932 | - |
$2,336
33,855
kWh
|
$596
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,054 | $403 |
$3,054
35,933
kWh
|
- | - | - | - | |
04 | 2.2135: Repair and eliminate steam leaks | $8,241 | $404 | - | - |
$8,241
-
MMBtu
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,679 | - |
$1,679
19,749
kWh
|
- | - | - | - | |
06 | 2.2153: Close off unneeded steam lines | $9,659 | - | - | - |
$9,659
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,307 | $10,651 |
$9,288
135,084
kWh
|
$2,019
-
kW-mo/yr
|
- | - | - | |
08 | 2.6212: Turn off equipment during breaks, reduce operating time | $803 | - |
$803
11,638
kWh
|
- | - | - | - | |
09 | 2.2515: Use optimum thickness insulation | $325 | $84 | - | - |
$325
-
MMBtu
|
- | - | |
10 | 2.2515: Use optimum thickness insulation | $324 | $372 | - | - |
$324
-
MMBtu
|
- | - | |
11 | 2.7135: Install occupancy sensors | $286 | $228 |
$286
4,140
kWh
|
- | - | - | - | |
12 | 2.7134: Use photocell controls | $1,978 | $30 |
$1,143
16,562
kWh
|
$835
-
kW-mo/yr
|
- | - | - | |
13 | 2.6218: Turn off equipment when not in use | $63,455 | - |
$57,481
833,031
kWh
|
$5,974
-
kW-mo/yr
|
- | - | - | |
14 | 3.1191: Change procedures / equipment / operating conditions | $83,200 | $5,350 | - | - | - |
$83,200
-
lb
|
- | |
15 | 3.1191: Change procedures / equipment / operating conditions | $17,472 | - | - | - | - |
$17,472
-
lb
|
- | |
16 | 4.131: Modify process to reduce material use/cost | $10,320 | - | - | - | - | - | $10,320 | |
TOTAL RECOMMENDED | $239,557 | $59,022 |
$97,784
1,223,555
kWh
|
$12,232
-
kW-mo/yr
|
$18,549
-
MMBtu
|
$100,672
-
lb
|
$10,320 | ||
TOTAL IMPLEMENTED | $28,671 | $921 |
$9,015
117,737
kWh
|
$1,431
-
kW-mo/yr
|
$18,225
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs