| Assessment Year | 2004 |
|---|---|
| Principal Product | Livestock Feed |
| NAICS | 115114: Postharvest Crop Activities (except Cotton Ginning) |
| SIC | 723: Beauty Shops |
| Sales Range | less than $500 k |
| # of Employees | 90 |
| Plant Area |
52,500
ft2
|
| Annual Production | 0
ton
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $162,940 | 1,973,286 |
kWh
|
$0.083 |
| Electricity Demand | $49,368 | 7,102 |
kW-mo/yr
|
$6.95 |
| Natural Gas | $46,902 | 5,067 |
MMBtu
|
$9.26 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $34,793 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $5,948 | $9,014 |
$3,613
65,687
kWh
|
$2,335
-
kW-mo/yr
|
- | |
| 02 | 2.1213: Direct warmest air to combustion intake | $4,683 | $24,500 | - | - |
$4,683
-
MMBtu
|
|
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,477 | $23,746 |
$6,391
116,192
kWh
|
$3,086
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,920 | $1,902 |
$1,450
30,608
kWh
|
$470
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,256 | - |
$2,256
27,378
kWh
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,861 | - |
$1,861
12,508
kWh
|
- | - | |
| 07 | 2.7124: Make a practice of turning off lights when not needed | $4,852 | $1,004 |
$4,572
83,123
kWh
|
$280
-
kW-mo/yr
|
- | |
| 08 | 2.7131: Add area lighting switches | $1,051 | $3,395 |
$1,051
12,737
kWh
|
- | - | |
| 09 | 2.2135: Repair and eliminate steam leaks | $2,746 | $800 | - | - |
$2,746
-
MMBtu
|
|
| TOTAL RECOMMENDED | $34,793 | $64,361 |
$21,193
348,233
kWh
|
$6,171
-
kW-mo/yr
|
$7,429
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs