Assessment Year | 2004 |
---|---|
Principal Product | Precision Sheet, Plate and Metal Fabrication |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $1 M to 5M |
# of Employees | 35 |
Plant Area |
18,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $15,899 | 252,312 |
kWh
|
$0.063 |
Electricity Demand | $8,711 | 1,464 |
kW-mo/yr
|
$5.95 |
Natural Gas | $72,801 | 5,287 |
MMBtu
|
$13.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,035 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,850 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $12,968 | $5,044 | - | - |
$12,968
-
MMBtu
|
- | |
02 | 2.7145: Install skylights | $3,241 | $8,578 |
$3,360
30,511
kWh
|
- | - | $(-119.0) | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $908 | $5,504 |
$651
9,168
kWh
|
$257
-
kW-mo/yr
|
- | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $942 | $210 |
$620
8,736
kWh
|
$322
-
kW-mo/yr
|
- | - | |
05 | 3.2173: Convert to robotic painting | $24,976 | $124,000 | - | - | - | $24,976 | |
TOTAL RECOMMENDED | $43,035 | $143,336 |
$4,631
48,415
kWh
|
$579
-
kW-mo/yr
|
$12,968
-
MMBtu
|
$24,857 | ||
TOTAL IMPLEMENTED | $1,850 | $5,714 |
$1,271
17,904
kWh
|
$579
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs