Assessment Year | 2002 |
---|---|
Principal Product | Cement Products |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 18 |
Plant Area |
600,000
ft2
|
Annual Production | 19,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,975 | 4,397,400 |
kWh
|
$0.050 |
Electricity Demand | $33,224 | 11,214 |
kW-mo/yr
|
$2.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,750 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,078 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,883 | $7,110 |
$3,082
61,631
kWh
|
$801
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $10,820 | $15,547 |
$7,245
144,908
kWh
|
$3,770
-
kW-mo/yr
|
- | - | $(-195.0) | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,012 | $230 |
$2,084
34,736
kWh
|
- | - | - | $(-72.0) | - | |
04 | 2.4133: Use most efficient type of electric motors | $8,442 | $10,641 |
$5,600
111,994
kWh
|
$2,842
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.3112: Store heated/ cooled water for use during peak demand periods | $13,799 | $202,500 | - | - | - | - | - | $13,799 | |
06 | 3.4155: Meter waste water | $1,066 | $1,700 | - | - |
$1,066
-
gal
|
- | - | - | |
07 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $728 | - | - | - | - |
$728
-
lb
|
- | - | |
TOTAL RECOMMENDED | $40,750 | $237,728 |
$18,011
353,269
kWh
|
$7,413
-
kW-mo/yr
|
$1,066
-
gal
|
$728
-
lb
|
$(-267.0) | $13,799 | ||
TOTAL IMPLEMENTED | $3,078 | $1,930 |
$2,084
34,736
kWh
|
- |
$1,066
-
gal
|
- | $(-72.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs