| Assessment Year | 2001 |
|---|---|
| Principal Product | Sulfuric acid |
| NAICS |
n/a
|
| SIC | 2874: Phosphatic Fertilizers |
| Sales Range | $10 M to 50M |
| # of Employees | 30 |
| Plant Area |
52,000
ft2
|
| Annual Production | 930,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $661,703 | 16,542,567 |
kWh
|
$0.040 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,902,856 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $38,570 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,848 | $2,526 |
$1,848
46,204
kWh
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $20,327 | $91,728 |
$20,327
508,874
kWh
|
- | - | |
| 03 | 4.111: Add equipment/ operators to reduce production bottleneck | $122,360 | $141,700 |
$122,360
3,000,059
kWh
|
- | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $1,652 | - |
$1,752
43,800
kWh
|
$(-100.0) | - | |
| 05 | 2.7135: Install occupancy sensors | $1,863 | $3,058 |
$1,863
46,584
kWh
|
- | - | |
| 06 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,741,926 | $6,200,000 |
$(-1,019,664.0)
86,975
kWh
|
- | $2,761,590 | |
| 07 | 4.431: Train operators for maximum operating efficiency | $12,880 | $9,000 |
$12,880
322,000
kWh
|
- | - | |
| TOTAL RECOMMENDED | $1,902,856 | $6,448,012 |
$(-858,634.0)
4,054,496
kWh
|
$(-100.0) | $2,761,590 | ||
| TOTAL IMPLEMENTED | $38,570 | $106,312 |
$38,670
967,462
kWh
|
$(-100.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Administrative Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs