| Assessment Year | 1999 |
|---|---|
| Principal Product | Treated Utility Poles and Marine Pilings |
| NAICS |
n/a
|
| SIC | 2491: Wood Preserving |
| Sales Range | $5 M to 10M |
| # of Employees | 25 |
| Plant Area |
1,744,900
ft2
|
| Annual Production | 1,300,000
thousand feet
|
| Production Hrs. Annual | 2,808
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $127,841 | 2,159,144 |
kWh
|
$0.059 |
| Electricity Demand | $33,327 | 6,726 |
kW-mo/yr
|
$4.95 |
| Natural Gas | $70,421 | 13,156 |
MMBtu
|
$5.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $217,555 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $213,783 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $3,222 | $2,085 |
$2,693
45,721
kWh
|
$529
-
kW-mo/yr
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $931 | $1,913 |
$931
15,826
kWh
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,429 | $1,800 |
$1,429
40,445
kWh
|
- | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $3,893 | $8,998 |
$3,342
56,565
kWh
|
$551
-
kW-mo/yr
|
- | - | |
| 05 | 2.6212: Turn off equipment during breaks, reduce operating time | $550 | - | - |
$550
-
kW-mo/yr
|
- | - | |
| 06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $1,395 | - | - | - | - | $1,395 | |
| 07 | 3.5317: Sell / offer by-product as animal feed | $18,760 | - | - | - | $18,760 | - | |
| 08 | 4.652: Replace existing equipment with more suitable substitutes | $187,375 | $44,000 | - | - | $187,375 | - | |
| TOTAL RECOMMENDED | $217,555 | $58,796 |
$8,395
158,557
kWh
|
$1,630
-
kW-mo/yr
|
$206,135 | $1,395 | ||
| TOTAL IMPLEMENTED | $213,783 | $56,711 |
$5,702
112,836
kWh
|
$551
-
kW-mo/yr
|
$206,135 | $1,395 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs