ITAC Assessment: UF0221
ITAC logo
ITAC Assessment: UF0221
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Treated Utility Poles and Marine Pilings
NAICS
n/a
SIC 2491: Wood Preserving
Sales Range $5
M
to 10
M
# of Employees 25
Plant Area 1,744,900
ft2
Annual Production 1,300,000
thousand feet
Production Hrs. Annual 2,808
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,841 2,159,144
kWh
Electricity Demand $33,327 6,726
kW-mo/yr
Natural Gas $70,421 13,156
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $217,555 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $213,783

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7111: Reduce illumination to minimum necessary levels $3,222 $2,085 $2,693
45,721
kWh
$529
-
kW-mo/yr
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $931 $1,913 $931
15,826
kWh
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,429 $1,800 $1,429
40,445
kWh
- - -
04 2.4133: Use most efficient type of electric motors $3,893 $8,998 $3,342
56,565
kWh
$551
-
kW-mo/yr
- -
05 2.6212: Turn off equipment during breaks, reduce operating time $550 - - $550
-
kW-mo/yr
- -
06 3.5248: Separate and recycle scrap metal to foundry or for sale $1,395 - - - - $1,395
07 3.5317: Sell / offer by-product as animal feed $18,760 - - - $18,760 -
08 4.652: Replace existing equipment with more suitable substitutes $187,375 $44,000 - - $187,375 -
TOTAL RECOMMENDED $217,555 $58,796 $8,395
158,557
kWh
$1,630
-
kW-mo/yr
$206,135 $1,395
TOTAL IMPLEMENTED $213,783 $56,711 $5,702
112,836
kWh
$551
-
kW-mo/yr
$206,135 $1,395
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs